Resolution is now ready
to sail from the Kentish Flats after finishing laying all
30 Foundations for the Windfarm
FOUNDATION INSTALLATION
COMPLETED
On Tuesday 19 October the last of the 30 monopiles was installed,
and the MPI Resolution left the site after a successful
effort.
The installation works have lasted about 61 days or 2 days
per foundation, including the required transportation trips
to Belgium to collect 5 complete foundations. This is very
satisfactory, especially as the weather has been quite poor
for the season. In addition, vessel leg penetration into
the seabed has in some cases exceeded 10 metres.
The completion of the installation works
has been achieved one month ahead of the original time schedule.
However, diving teams will continue working on the foundations
to complete the internal tubes for the submarine cables
between the turbines and cables to shore.
|