Construction Ship Resolution Laying Foundations for the windfarm on the kentish flats off Whitstable

Windfarm Foundations.
First, the foundation will be placed. It is a cylindrical steel tube with a diameter of about 4 metres and a material thickness of 4.5 cm. As specially designed jack-up vessels with heavy-duty hydraulic hammers will be used to drive the mono-pile some 28 to 34 meter metres into the seabed depending on the geology of the sea bottom.

Monopile and Transition piece on the deck of the resolution awaiting to be lifted into position
Monopile being readied for lifting by having the upending tool attached
Monopile being lifted from the deck and craned into position of the stern of the ship to be piled into the sea bed using a hydraulic hammer